Kiln
4 Update
Agreement
has been reached with Pirson regarding operation of the large crane
for construction on the preheater Tower. A large concrete slab is
being laid alongside the
kiln,
to provide a stable base upon which the crane can operate.
Work
will then start
on
completing the top floor and 1st
stage
cyclone
Refractory
work has been completed in the cooler and the lower stage cyclones
in the
Preheater
tower.
Cladding
has commenced in the Raw & Coal Mill areas and will progress
quickly
over
the coming weeks.
Both
robotic cranes have been installed in the Crane Gantry and the
suppliers are
currently
commissioning them. Work is ongoing refurbishing the conveyor
gantries
for
the Limestone delivery to kiln 4 Raw Mill.
There
are now 5 full time members of the commissioning team. They have
been
carrying
out acceptance checks on machinery in the raw Mill & Cooler
areas. It is
proposed
to put electrical power onto the Raw Mill area on the 4th
February,
so cold
commissioning
can start in this area
Work
has commenced installing the tanks on the Cemfuel Tank farm.
|